Expansion of the mining activity in the Namibian desert called for a demand of water giving rise to the Mile 6 pipeline. The pipeline was installed near the reservoir in Swakopmund and consisted of 5000m of DN1200/PN16/SN5000. Aggressive soil conditions made FLOWTITE the pipe of
choice in these corrosive conditions. Biggest challenge was to open the trench as the sand is only 300mm-600mm deep before bed rock is reached. Blasting through the rocks made the project time consuming.
| Product Type | Flowtite Pressure Pipe |
| Application | Raw Water |
| Total length (m) | 5 094 |
| Diameter DN min/max (mm): | 1 200 |
| Pressure PN min/max (bar): | 16 |
| Joint types | Flowtite REKA Coupling |
| Fittings (Qty) type: | Bends, Rocker pipe, Airvalve Tee & Scour Tee |
| Installation type | Above Ground and Buried |
| Completion date | 2015 |
| End User | Nam Water |
| Consulting Engineer | Nam Water |
| Contractor | China State Construction SA (CSNJV) |